khughes

Falcon Stadium Construction Update/February 7

 Uncategorized  Comments Off on Falcon Stadium Construction Update/February 7
Feb 092017
 

At Falcon Stadium, crews are in the process of constructing the home concession stand, and they’re about to start pouring concrete for the locker room. The visitor bleachers are complete. Soon, the home bleachers will go up, and roof trusses will be installed.

Jeremiah Gray Construction Update/February 7

 Uncategorized  Comments Off on Jeremiah Gray Construction Update/February 7
Feb 092017
 

Exciting signs of progress at Jeremiah Gray Elementary. The connector between the main building and the Kindergarten Academy is up! Also, the playground equipment has arrived!

Homecroft Elementary Construction Update/February 7

 Uncategorized  Comments Off on Homecroft Elementary Construction Update/February 7
Feb 092017
 

The Kindergarten Academy is coming along at Homecroft Elementary. The dry wall is up, the windows are going in, and crews are hard at work to get the school ready to welcome students this fall. Also, the church next door will soon come down, and the property will become green space.

Winchester Village Construction Update/February 7

 Uncategorized  Comments Off on Winchester Village Construction Update/February 7
Feb 072017
 

The portable classrooms at Winchester Village are being removed as students get settled in their new classrooms. The new office and entrance area is also complete. The final phase of construction is expected to be finished in April.